top of page
PT Engineering developed a traffic simulation using TransModeler software for I‐5986, which includes widening I‐95 to eight lanes from the I‐95 interchange with I‐95 Business/US 301 (Exit 56) in Cumberland County to the I‐95 interchange with I‐40 in Johnston County. The proposed improvements include adding two lanes on I‐95 in both directions and a new ramp at the I‐295 interchange to complete the missing movement from I‐95 northbound to I‐295 westbound. The study included the analysis of the 2018 existing conditions and the 2040 Scenarios for both the No-Build and Build scenarios. The results of this analysis for this project will also be included in an Interstate Access Report that will also completed by PT Engineering.
bottom of page